Construction Committee Meeting Saturday April 10, 2013 6:30 PM – 9:30 PM

Attendees: Mr. YoungKun Joh Dr. Jung Hi Lee, Dr. Sam Sim , Mr. Cliff Lee ,  Ki Hoon Cha

At :  Asian Bistro

I. Discussion of choosing Site Engineering Company

a. At first, two companies – RBS (Mr. Bob Weatherford ) and Gianforcaro – have been chosen out of the four who sent the proposal. The other two companies’ proposed costs were too high.

b. After the extensive discussion and careful review, the attendees agreed to work with RBS unanimously but under one condition. which is to have an interview with Mr. Mr. Bob Weatherford ( RBS ). Mr. Sim will make sure with the company that there would be no extra expenses and hidden condition.

II. Agreement on hiring the lawyer Solomon

III. Discussion of  ways to choose an architect at a fair and reasonable cost